HomeMy WebLinkAbout2016-0292 Final Packet ELECTRICAL ONLYIthaca, NY 14850
215 N. Tioga Street
Town of Ithaca
Owner:Garuda Hotels
Located At:1100 DANBY ROAD
Applicant Information
10/24/2018Expiration Date:
Date:10/24/2017
ELECTRICAL ONLYPermit Type:
Building Permit #:2016-0292
37.1-1-9SBL #:
Ithaca NY 14850
408 Second St
Shisler Electrical Contractor, Inc
Inspections
-ELECTRICAL - FINAL ELECTRICAL PASSED 11/28/2017MKELLY
Notes: Install 9 bollard light fixtures by front sidewalk.
Results: Dana Magnuson and I met on site with Lloyd Shisler jr. and his son Brandon, contractor's reps. Loyd opened up
junction boxes & panel as I requested. No rough in violations noted.
-ELECTRICAL - ROUGH CANCELLED 11/16/2017DMAGNUSON
Notes: Rescheduled: - Met with Lloyd jr. and his son Steven Shisler. Existing PVC conduit was dug up to verify trench
depth in several areas. Most of the PVC was at a 16-18'' depth. There is an existing 2' PVC conduit that comes from under
concrete to the bollard to the immediate right of the entryway that is 16''. I told Lloyd jr. to lay caution tape throughout the
entire pipe run (which is in a flower bed). I went inside and spoke with hotel owner Ilanya Bobroff and manager Sidney and
told them about the additional digging required to complete the project. They were ok with the news. Lloyd jr. is planning on
laying the caution tape today and burying it as he goes. He said Steven will take photos and I said that was ok and I will
also stop back later this afternoon to verify thae caution tape. Verified new THHN wire (replaced UF) in existing light pole
on south side of building that the bollards are all fed from.
Results: No electricians on site.
-TRENCH CANCELLED 11/16/2017DMAGNUSON
Notes: Rescheduled: - See electrical rough in notes from today 11/16/17.
Results: No electricians on site. No dirt dug up since I was there this morning.
-CONSULT COMPLETED 10/16/2017MKELLY
Notes: 1.26.17 ORDER TO REMEDY SENT. LK Install 9 bollard fixtures by front sidewalk on existing electric system
installed for previously removed lighting - Country Inn & Suites.
Results: Cindy S. called to discuss Appearance ticket for country Inn & Suites. I asked Bruce. Judge is the only one who
can change it now - we both to appear. She said that she didn't even work there when this project was done, so she was
asking for the history. I explained it from my perspective & offered to send her the emails.
-CONSULT COMPLETED 11/2/2017MKELLY
Notes: Install 9 bollard light fixtures by front sidewalk.
Results: I called Cindy Stonecipher, Administrative Assistant, at Garuda Hotels - 256-1100. She is the owner's rep who
met in court and picked up the Permit. I told her that I had heard nothing from the contractor, Shisler Electric, about
arranging the inspection that we agreed upon in court. She said that she had emailed them once. She will now push them
harder.
-CONSULT COMPLETED 11/13/2017MKELLY
Notes: Install 9 bollard light fixtures by front sidewalk.
Page 1 of 3
Ithaca, NY 14850
215 N. Tioga Street
Town of Ithaca
Results: I discussed w/ court clerk about this case. I called Cindy S., at Garuda Hotels (owner's rep in court) to say I've
heard nothing from Shisler. She said that she has called & left message with them before, but has heard nothing back
from them - she will push them to get this done.
-FOLLOW UP COMPLETED 5/23/2017MKELLY
Notes: 1.26.17 ORDER TO REMEDY SENT. LK Install 9 bollard fixtures by front sidewalk on existing electric system
installed for previously removed lighting - Country Inn & Suites.
Results: Reviewed & met w/ Lori about issuing Court Appearance Ticket. She to pursue.
-FOLLOW UP COMPLETED 12/13/2017MKELLY
Notes: Install 9 bollard light fixtures by front sidewalk.
Results: Review & letter to Court requesting ''dismissal without prejudice. See ltr here in Docs.
-PRE-BP SITE INSPECTION COMPLETED 10/24/2017MKELLY
Notes: Install 9 bollard fixtures by front sidewalk on existing electric system installed for previously removed lighting -
Country Inn & Suites.
Results: Site remains with bollard lights installed without a BP. As per agreement in court, I am issuing BP, then contractor
is to arrange inspections & corrections as needed.
-PRE-BP SITE INSPECTION FAILED 7/19/2016MKELLY
Notes: Install 9 bollard fixtures by front sidewalk on existing electric system installed for previously removed lighting -
Country Inn & Suites.
Results: Lights completed without Permit after contractor and Hotel manager told in email to stop until Permit has been
issued. No formal inspection done at any time, but it appears from looking at the light fixtures they do not meet the TOI
dark sky code. Previous exterior lights there were removed because they did not meet coded - existing electric may have
never met code - inspect all.
-ELECTRICAL - ROUGH PARTIAL 11/16/2017DMAGNUSON
Notes: Install 9 bollard light fixtures by front sidewalk.
Results: Met with Lloyd jr. and his son Steven Shisler. Existing PVC conduit was dug up to verify trench depth in several
areas. Most of the PVC was at a 16-18'' depth. There is an existing 2' PVC conduit that comes from under concrete to the
bollard to the immediate right of the entryway that is 16''. I told Lloyd jr. to lay caution tape throughout the entire pipe run
(which is in a flower bed). I went inside and spoke with hotel owner Ilanya Bobroff and manager Sidney and told them
about the additional digging required to complete the project. They were ok with the news. Lloyd jr. is planning on laying
the caution tape today and burying it as he goes. He said Steven will take photos and I said that was ok and I will also stop
back later this afternoon to verify thae caution tape. Verified new THHN wire (replaced UF) in existing light pole on south
side of building that the bollards are all fed from.
-FOLLOW UP PARTIAL 3/10/2017MKELLY
Notes: Install 9 bollard fixtures by front sidewalk on existing electric system installed for previously removed lighting -
Country Inn & Suites.
Results: See emails in Permit Docs.
-FOLLOW UP PARTIAL 10/19/2017MKELLY
Notes: Court Appearance - see in Complaints
Page 2 of 3
Ithaca, NY 14850
215 N. Tioga Street
Town of Ithaca
Results: I, Martin Kelly, met in Town Court - Judge Salk presiding. Cindy Stonecipher, Administrative Assistant
of Garuda Hotels (owner's rep.), attended, as well as Lloyd Shisler, electrical contractor. I requested, and it was agreed
upon by owners rep:
Double fee - an additional $200
Entire system inspected by Town of Ithaca
Violations corrected
Judge Salk adjourned until 12/14/17 at 9 AM
>>>>>>>>>
Owner's rep paid the additional $200 fee today.
I to complete review and send Permit to owner w/ email copy to both owner & contractor.
Contractor to then call and schedule inspection.
Contractor to correct all violations.
-PRE-BP SITE INSPECTION PARTIAL 2/7/2017MKELLY
Notes: Failed Previous Inspection: - Lights completed without Permit after contractor and Hotel manager told in email to
stop until Permit has been issued. No formal inspection done at any time, but it appears from looking at the light fixtures
they do not meet the TOI dark sky code. Previous exterior lights there were removed because they did not meet coded -
existing electric may have never met code - inspect all.
Results: I went and looked at the bollard lights they installed despite my email of 7/1/16 (a copy is here in Municity
application packet) saying to make sure to get the lights approved and have the Permit before installing them - the lights
do not meet the TOI dark sky rule. Cate from Shisler Electric called me - we discussed the situation, and after I told her
the date of my email, she was able to retrieve it on her end - then promised to further research it and get back to me.
-TRENCH PARTIAL 11/16/2017DMAGNUSON
Notes: Install 9 bollard light fixtures by front sidewalk.
Results: See electrical rough in notes from today 11/16/17.
-ELECTRICAL - ROUGH PASSED 11/28/2017MKELLY
Notes: Rescheduled: - No electricians on site.
Results: Dana Magnuson and I met on site with Lloyd Shisler jr. and his son Brandon, contractor's reps. Dana approved
trench based on this & previous inspections. Loyd opened up junction boxes & panel as I requested. No rough in
violations noted.
-FOLLOW UP PASSED 12/14/2017MKELLY
Notes: Install 9 bollard light fixtures by front sidewalk.
Results: Reviewed, notes, issued CC, emailed to owner, & notified Town court that we have approved the project and
closed out the Complaint.
-TRENCH PASSED 11/28/2017DMAGNUSON
Notes: Rescheduled: - No electricians on site. No dirt dug up since I was there this morning.
Results: Martin Kelly and I met with Lloyd Shisler jr. and his son Brandon. We discussed trench photos Brandon emailed
last week and I verified that the trench photos were from different sections.