HomeMy WebLinkAboutSJS 2000
1
SPECIAL JOINT SUBCOMMITTEEJANUARY 18, 2000
A regular meeting of the Special Joint Subcommittee was held on January 18, 2000, at
12:30, at the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New
York
PRESENT: *Frank Liguori, Town of Ithaca
Jim Schug *Mary Russell, Town of Ithaca
*Cathy Valentino, town of Ithaca
Gary Gleason, Chief Operator
Bill Gray, City Superintendent
Larry Fabbroni, Asst. Super W & S
Brent Cross, Village of Cayuga Heights Engineer
David Herrick, TG Miller, P.C.
Jerry Hook, Stearns & Wheler
ABSENT: *Joseph Leonardo, City of Ithaca
*Steve Ehrhardt, City of Ithaca
Dominick Cafferillo, City Controller
*Dan Walker, Town of Ithaca
*Steve Ehrhardt, City of Ithaca
*Alan Cohen, City of Ithaca
*Ed Hershey, City of Ithaca
*Mark Varvayams, Town of Dryden
Cathy Valentino, Vice Chair, opened the meeting.
1. Approval of December Minutes
Postponed until the next meeting, no quorum.
2. Updates on SEQR, if any
Larry introduced Jerry Hook from Stearns & Wheler. Jerry reported that there is a meeting
in the morning of January 27th in Cortland to discuss SEQR requirements for the next phase
of the project and schedule work elements. The larger Intermunicipal Agreement is on
the list to discuss on the 27th, that needs to move along.
2
Jerry mentioned that we are also going to talk about scheduling a scoping session.
3. Updates on DEC items, if any.
Brent Cross, Cayuga Heights Village Engineer, quoted Mayor Anderson saying that the
Mayor felt that the sooner action was taken, the better for all parties.
Cathy thought it would be helpful if we received a quick summary of the project including a
structure and time frame in addition to the funding amounts.
4. Staff Reports
Gary handed out a proposal prepared by Hershey Energy System that outlined the
implementation of a process that would result in uniform and controlled electrical
consumption resulting in significant savings to the owners for utilities. Basically, the
proposal which required the installation of sophisticated equipment costing about $90,000,
would result in savings to the owners that would constitute more than the cost and the
equipment would then be paid for out of monies saved resulting in no extra cost for the
system. Gary also mentioned that he had involved Auburn Armature personnel in the
review of the proposal and was informed by those individuals, that, because of the
guarantee included in the Hershey Proposal, the owners should enter into an agreement
with Hershey, if and only if, the attorneys for the municipality agreed that the guarantee
was truly what it appeared to them to be. The SJS was requested to review the proposal
prior to the meeting in February when the Hershey representatives would make a formal
presentation of their project to the SJS. In addition, a copy of the proposal would be
sent to Attorney Susan Brock and her presence would also be requested for the meeting in
February. It is anticipated that at that meeting, Susan Brock will advise the committee on
the credibility of the proposal and warrantee.
5. Financial Reports
Nothing to report.
6. Old Business
- Year 2000 Schedule of Meetings
Larry thought for all that we have going on, we should meet every month for at least 6
months. Keep it as the 3rd Tuesday @ 12:30 PM. February 15th will be the next meeting
date.
3
7. New Business
8. Adjournment
The next regularly scheduled meeting is set for February 15th @ 12:30 PM.
1
SPECIAL JOINT SUBCOMMITTEEFEBRUARY 15, 2000
A regular meeting of the Special Joint Subcommittee was held on February 15, 2000, at
12:30, at the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New
York
PRESENT: *Frank Liguori, Town of Ithaca
*Mary Russell, Town of Ithaca
*Cathy Valentino, Town of Ithaca
*Mark Varvayanis, Town of Dryden
*Ed Hershey, City of Ithaca
Gary Gleason, Chief Operator
Bill Gray, City Superintendent
Larry Fabbroni, Asst. Super W & S
Susan Brock, SJS Attorney
Ray Davis, Hershey Energy
,Hershey Energy
,Hershey Energy
Jerry Hook, Stearns & Wheler
Brent Cross, Village of Cayuga Heights Engineer
Steve Thayer, Deputy Controller
Dominick Cafferillo, City Controller
Dan Walker, Town of Ithaca
ABSENT: *Joseph Leonardo, City of Ithaca
*Steve Ehrhardt, City of Ithaca
*Alan Cohen, City of Ithaca
Cathy Valentino, Vice Chair, opened the meeting.
1. Hershey Energy Presentation
Background: The Hershey proposal referred to a contract between Hershey Energy and
the IAWWTF that would result in the installation of certain electroflo equipment (invented
and fabricated by Hershey) proprietary to Hershey, which, after installation, would result in
significant savings to the IAWWTF in electrical costs. Briefly, the proposed equipment
would stabilize electrical energy resulting in increased efficiency of consumption.
2
There are two methods of purchase for the equipment. One time payment of $90,000.
or
Payments monthly for five years of about $2,070 per month. Using this scenario a
guarantee of about $100 savings over and above the cost of the equipment payment of
$2,070 was included in the proposal. Although that figure of $100 was guaranteed, the
actual expected savings would be $1,548. At the end of the five year lease period, all
savings would be realized by the IAWWTF.
Hershey actually prepared a proposal for the IAWWTF on May 19, 1999 and this proposal
was reviewed by staff and presented to Susan Brock, Attorney at Law for further review and
interpretation of the contract as illustrated in the proposal. Staff had included
representatives from Auburn Armature to assist in review of the proposal as the program
applied to the IAWWTF. Auburn Armature and Staff agreed that the proposal regarding
technology was sound as long as the guarantee was also sound as it appeared.
At the meeting of this date, the proposal was handed out to each member present.
After a short presentation by the Hershey representatives, Susan informed those present
that the guarantee in the contract, as proposed was not truly for the five years ( the lease
period) but for only the first year.
Hershey representatives replied that the intention was for the guarantee to last for the life
of the lease period of five years and that an addendum would be presented to the IAWWTF.
Several questions were asked of the Hershey representatives including queries about results
from other installations, other payment requirements for such items as replacement of
failed equipment, and a listing of new installations with a tract record of savings.
Hershey representatives provided a listing of new installations and added that a
maintenance contract would be provided at a cost to the IAWWTF which would provide for
replacement of failed or damaged equipment.
The representatives of Hershey Energy Systems were informed that approximately three
months would be needed for staff to communicate with similar installations. Meanwhile,
Hershey representatives would address the concerns regarding the proposal of Staff,
members of the SJS, and the SJS consulting engineer, Stearns and Wheler, (Jerry Hook).
3
2. Approval of December, 1999 Minutes & January, 2000 Notes
Cathy asked for a motion to approve the December Minutes and January Notes. The
motion was made and seconded. All were in favor and the motion was carried.
3. Updates on SEQRA
Jerry Hook mentioned that there was a meeting with overview of project at the DEC in
Cortland. There were a few action items that came from that meeting, one of them being
prepare an overview document, being requested by DEC as the lead agency. Jerry had 6
six copies of the draft to distribute to the six municipalities, comments requested back
ASAP. This document is for the purpose of taking the 1999 Unified Engineering Report and
summarizing it, in a brief format. The one thing that is missing from here is a discussion of
the Intermunicipal Agreement and its status. Jerry thinks the approach that needs to be
taken is for SEQRA to proceed to scoping. By each individual municipality signing the
unified engineering report, you basically agree to the physical concept of an Intermunicipal
agreement in terms of flow distribution. That is flow coming from Lansing through Cayuga
Heights being diverted to the IAWWTF. The actuality of how that is paid whether it is as
customers or partners, is not pertinent to the SEQRA process. If everyone is in agreement,
Jerry will proceed with that aspect.
Cathy mentioned that one of the things they asked up front was an agreement on some
kind of oversight committee. We have to name a government entity that would be the
fiscally responsible processor. Jerry said that is if there is a permanent bond act
application.
Jerry also mentioned that for DEC to legitimately be the lead agency, there needs to be a
permit application that involves the DEC. We agreed at the meeting the easiest permit
application we can get in place would be the required modifications for Cayuga Heights and
the IAWWTF. So we are working on drafting those applications and will have them within
a couple of days, waiting for data from Cayuga Heights. One of the decisions that need to
be made is what actual phosphorus limit should we request. There is no mandate or
regulation that is driving the state to issue a new phosphorous limit for either one of these
plants. The best thing that they can hang their hat on right now, is a no net increase.
They want us to go to a much lower limit. The technology that we are putting in, we feel
comfortable saying we can get down .2 mg/l, but right now with what is in the engineering
report that is being submitted, that technology will not treat the entire flow. It will treat
9.4 mgd with the potential of going up to 13 mgd. The current permit is at 1 mg/l. A very
conservative approach would be to ask the State, seeing how this is a voluntary upgrade, we
want to request our limit to be written as .4 mg/l.
4
Larry felt comfortable with .4 mg/l. Brent isn’t comfortable going that far. Brent wanted
to know why we couldn’t go with .5 mg/l.
Jerry said we don’t need to make a decision today, when we get the draft permit, then we’ll
have to look closer. Next scoping session will be March 2nd at the Corltand DEC Office.
Mary had a question, about the planning area.
4. Updates on DEC items
Larry reported that at the end of February, beginning of March, we’ll hear on this round of
funding. Brent thought what he heard at the Cortland meeting that there was no time
table and it would depend on our actions. They weren’t going to give a timetable, they
expected us to do certain things. Judge how much money we deserve to get, so to speak,
based on our actions, and based on our intermunicpal agreement progress. Or even more
specifically the spending of the dollars we have already been offered. Brent is of the
impression from a personal discussion with Steve that if we don’t do one or both of those
things, there is no money.
Larry said that Steve is giving conflicting massages out. Larry had the opportunity in NY to
talk with Steve’s main assistant Jim Burke, because he tends to be more of the engineering
type who doesn’t give you a whole bunch of foam. Steve is getting a lot of pressure from
Albany about us moving forward with the first money we got. Jim Burke said, that as far as
he new, all of the recommendations for the second round that the region made to Albany
were still in the works. What that meant, is they went in and asked for 7 of the 14 million,
5 of which was going to filtering and 2 split to Lansing sewers and City/Town interceptors.
So that is as much as we know and Jim was more definite about the act that nothing much
had changed since October. Steve is getting pressure to start using the first money from
1998.
Gary didn’t know how we could select a process until we know how much money we have.
Susan thought he said put all of the unified engineering report projects in right now and if
certain things don’t get funded, things get pulled out of the SEQR. Susan reported that he
said we could get some money right now, the project phase 1 interceptor work has already
been done. Submit the paperwork and sign contracts and that money could be awarded
now and you wouldn’t have to wait for anything else to happen.
Larry is working on that, Dominick has been away. Brent thought there needed to be
some discussion about that.
5
Brents understanding is that the items that are already completed were offered as part of
the project on the basis of the joint application we’d have to be willing to commit to all or
none, Larry said that’s not correct. The City received money for specific projects as part of
the joint application. Those were the project ready aspects. The 2 million that was
already spent was an awful strong project ready part of the joint application and nobody
else had 2 million spent. Lansing had a lot of planning in their report and you showed a lot
of engineering. Brent said that based on the fact that you had already payed for it was the
basis that for the local share. Larry interjected, projects since November of 1996 is the
key. Any projects done subsequent to the passing of the bond act in November 1996, we
are eligible for the state funding. Doesn’t matter that they were done, it mattered that
they were done after the act was passed. Brent’s bottom line is irrelevant to the sematics
of that. It is that we may not get all of the money we are asking for and if you spend some
money on certain things now, Brent would just like to know that it is going to count to the
total project.
Dominick mentioned that we are trying to use this initial aspect of leverage to additional
funding.
Mary asked, when they deliver the money is there some sort of legal document... Larry
said they will draw up a contract and sign it, which we have not signed contract 1 yet. We
asked for 6 million for the interceptor costs and we are going to get 2 of that. Larry
doesn’t see the problem in asking for the first 1.22 million for exactly what they told us we
could have it for. Cathy said we have to spend it on that and if we don’t, then it will
jeopardize us in getting more money in the future, so there really isn’t any other alternative.
Brent said his answer is because when the come back and give me more money and when
it’s less than what we’ve asked for, there may be a problem. Larry seems to have more
insight in that the money awarded to specific projects in September 1998 will not change
with the results of the second round of funding.
5. Staff Reports
Skip for this meeting.
6. Financial Reports
Nothing to report.
7. Old Business
Nothing to report.
6
8. New Business
Nothing to report.
9. Adjournment
All were in favor!!
Next regularly scheduled meeting is set for March 21st @ 12:30 PM.
1
SPECIAL JOINT SUBCOMMITTEEMARCH 21, 2000
A regular meeting of the Special Joint Subcommittee was held on March 21, 2000, at 12:30,
at the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New York
PRESENT: *Frank Liguori, Town of Ithaca
*Mary Russell, Town of Ithaca
*Cathy Valentino, Town of Ithaca
*Mary Gutenberger, City of Ithaca
*Mark Varvayanis, Town of Dryden
*Ed Hershey, City of Ithaca
Gary Gleason, Chief Operator
Larry Fabbroni, Asst. Super W & S
Jerry Hook, Stearns & Wheler
Steve Thayer, Deputy Controller
Dan Walker, Town of Ithaca
Steve Farkas, Town of Lansing
David Herrick, TG Miller PC
ABSENT: *Joseph Leonardo, City of Ithaca
*Alan Cohen, City of Ithaca
Don Hartill, Village of Lansing
Bill Gray, City Superintendent
Susan Brock, Attorney
Dominick Cafferillo, City Controller
Ron Anderson, Village of Cayuga Heights
Brent Cross, Village of C.H. Engineer
Cathy Valentino opened the meeting and informed who was there that there is not a
quorum. But later there was a quorum.
1. Approval of February Minutes If Received
Not received.
2
2. Updates on SEQR, if any
Jerry informed the committee that a few comments came back on the Overview Document
from the original planning group and we are trying to get the document finalized, a few
things are still missing and then it will be redistributed. The things still missing are the
planning areas and some general wording about the possible agreements.
The other things that we did was prepare a request for qualifications for firms that are
capable of doing the EIS. We have received some comments back on the RFQ. We
would like to get it out by March 31, 2000.
3. Updates on DEC Items, if any
Jerry informed the committee that the state to continue to function as the lead agency,
needs the wastewater plant permit applications through DEC and so he would like to
submit the SPDES permit modifications for the Cayuga Heights Plant and the IAWWTF.
The draft permits are submitted to Larry, Cayuga Heights and Brent. We three met and
agreed on what we should submit as a request for phosphorus limit 0.4 for IAWWTF and 0.5
for Cayuga Heights, and the state is going to be looking to get that. Right now they are
acting as lead agency without any official application for permit. We did find that back in
1995, a request to upgrade to 13.1 MGD was submitted and we are pursuing that with the
State right now. What we want to do is have them take action on that permit
application. Basically we want to take the expansion of the plant of what has already been
done out of this new SEQRA process. The new work will permit the phosphorus removal
upgrade. We resubmitted to the State. They haven’t given the determination. They
may be pushing it into a stress test of the final settling tanks that will pretty much be a
formality.
Larry added that he received a letter from Senator Seward reiterating his interest in the
current Bond Act application.
4. Staff Reports
Gary mentioned that at the SJS’s leisure, review the handout of the 1999 Annual Report.
Larry also mentioned that he and Dan came to a draft 5 year plan on the interceptor. Larry
expects that before to long we will be talking about it. Larry referred to the map on the
wall, some improvements of which are tied up in the grant application also. These
interceptor capital costs and O&M are to be shared by flow.
3
The draft map identifies up to 18 different lines through the City that services the Town of
Ithaca or the Town of Dryden. Some of the lines from the north become crucial
connections to the Cayuga Heights, Village of Lansing and the Town of Lansing. The good
news is many of those parts we call Phase 1 of the Unified Plan are already built. We are
just waiting to see what this Bond Act round brings us before we can concretely discuss final
shares.
Cathy asked if this was in the draft agreement, Larry said there was a part on interceptors.
Dan mentioned that conceptually the 3 partners agreed. We need to figure out a final
map and plan.
Cathy said she would like to see an official copy of the draft map. Cathy would like Dan to
put it on the next town board agenda.
Larry said to excuse the inconsistences between what you see as Phase 1, 2, and 3 in the
grant application and what the 3 of us including Dave Putnam drafted up as some projects
were grouped for Bond Act funding and our discussions were focused on a rolling five year
plan.
Mary asked Larry what was the big issue for Dryden. Larry said we have been discussing
percentages in general, of an interceptor budget as opposed to an individual apportionment
for each of the 18 lines. As Larry pointed out, as an example, if you extend sewer out the
developed part of Ellis Hollow as shown on the planning area map or the German Cross
Road along Route 79, they are not currently service routes. But how do you try to figure
out fair value for the Town line on Slaterville Road, or the City lines all the way back to the
treatment plant. If we all share it in massy percentage flow, it is much more manageable
from a budget point of view. It is more steady state without peaks and valleys of requests
and budget impact.
Larry said that in the 2000 Budget, we allocated money for a belt press and would like to
move forward on it. Larry was absolutely positive that we would not see a penny of the
money for the belt press out of the Bond Act grant money still to be announced. Larry just
wanted a consensus to start getting the belt press purchase going. There was unanimous
agreement to move forward.
5. Financial Report
Steve said they are working on the 1999 Final Financial Report. He said there was also a
rumor of SJS needing more financial information. If what Paige provides isn’t enough, let
him know. Cathy thought that was appropriate, but a revenue account would be helpful.
Steve will take care of that. On the amounts that are closed, Steve will have to provide
4
that also.
5
6. Old Business
Cathy told Mark we were talking about the map for Dryden and we raised the question
again about the Hanshaw Road and the DOT. Do you have any idea what may be going on
with that? Mark said not much, but Barbara Blanchard wants it kept on the table, but she
can’t currently ensure DOT going in there and the County isn’t making a commitment to all
at that site yet. She has other sites she is looking at. Cathy’s next question is, for the
purpose of the map for the unified joint sewer project, should we be including that area?
Mark said it would be appreciated. Mark again mentioned that they wanted the DOT and
the 911 facility together and 911 has a deadline, so the County may be moving to
somewhere they can go right into. But, if it is in at least the impact analyses will be
included.
Jerry Hook said for SEQR it is better to include it now than not. Larry mentioned the
boundaries on the map as shown did not include this area as it reflected current committee
outcomes. Cathy thought maybe should this be discussed again with the other sewer
meeting before the next scoping session. Mary thought so also. Cathy will contact Alan
regarding this discussion and meeting.
7. New Business
Nothing to report.
8. Adjournment
All were in favor.
Next regularly scheduled meeting is set for April 18th @ 12:30 PM.
1
SPECIAL JOINT SUBCOMMITTEEAPRIL 18, 2000
A regular meeting of the Special Joint Subcommittee was held on April18, 2000, at 12:30, at
the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New York
PRESENT: *Frank Liguori, Town of Ithaca
*Cathy Valentino, Town of Ithaca
*Mark Varvayanis, Town of Dryden
Larry Fabbroni, Asst. Super W & S
Dan Walker, Town of Ithaca
Charlie Hatfield, Town of Dryden
Steve Thayer, Deputy Controller
Dominick Cafferillo, City Controller
Don Hartill, Village of Lansing
Dave Putnam, TG Miller Eng.
ABSENT: *Joseph Leonardo, City of Ithaca
*Alan Cohen, City of Ithaca
*Mary Russell, Town of Ithaca
Bill Gray, City Superintendent
Susan Brock, Attorney
*Ed Hershey, City of Ithaca
Gary Gleason, Chief Operator-IAWWTF
Cathy Valentino opened the meeting and informed who was there, that there was not a
quorum.
1. Approval of February & March Minutes
2. Updates on SEQR,
Cathy asked what updates if any were there. Larry said that depends on the SJS in terms
of the complexity of SEQRA. One thought tells you with this modest amount of money, it
could be simpler. The other thought tells you, you have to go through the process to be all
inclusive. You really can’t scale down the process as it relates to the Lansings and Dryden
without getting into the issue of segementing. It is worth a discussion before we go back
to DEC about what areas already funded could be expedited, but that doesn’t leave a whole
lot of time. The next meeting is the 29th.
2
3. Updates on Regional Planning
Cathy said their last meeting they were waiting for Bill Gray to arrive. Don asked if there was
any understanding where the grant money actually is. Larry said the Finger Lakes money is
still there. The $1.2 million the City spent already, the city bonded long term through the
EFC, so then the next question we asked, was, what additional interceptor work can be
done. DEC said let’s meet with the EFC fiscal people and see how open minded they
would be to utilize it for another part of the interceptor program.
Larry handed out a follow up list of capital projects and costs for a five year interceptor
program from last month. It is a draft that goes with the interceptor maps Larry sent
everyone. Larry thought maybe we could use this money already granted for interceptor
replacement, but DEC didn’t know exactly how to go about it. Some of this work has
nothing to do with the SEQR issues related to expanding the suggested area the plant would
serve.
Dominick said he would explore the transfer the grant money versus the borrowed money.
Dominick thinks it could be worked out.
4. Updates on DEC Items, if any
Larry reported that he, Gary, Bill & Jerry Hook had a meeting with NYSDEC on Friday the
14th. One point of the meeting was the rerating of this plant. DEC did find that we went
through SEQRA. So that issue is put to rest. The rest of the meeting was about what
protocol DEC wants us to follow in terms of stress testing this plant. What that involves is,
taking down 2 of the 4 final tanks and matching it with the flow that is roughly half of what
we might experience in a peak event. So that we can prove half of that flow, going
through half of our capacity is treated adequately. Currently, Ron and his staff are taking
care of things. We will be going through a 2 week stress test period starting next Monday,
April 24, 2000. DEC wants 7-8 different criteria’s sampled. We had a quick agreement on
what they want us to monitor. Then DEC outlined that we would submit that data, they
would review it, send it to their people in Albany, come back and make a determination or
rerating. It would have a 30-60 day public review, at that point, roughly a 4-5 month
process overall.
In regard to the announcement of the $4.1 million of Bond Act Funds, Tara from DEC
handed out a sheet of her best estimate of what monies we have been awarded to date.
DEC’s explanation of the 4.1 million, is the money already committed earlier by the
governor in September 1998 and not what we call additional monies awarded. Larry said
we got $7.4 million in the first place, but they resolved all of that by Tara’s handout at $7.5
million.
3
4
That is quite a disappointment from where we thought we were headed. We gave them
the press releases, the backup from Albany, but it didn’t seem to make a difference.
Frank asked what items weren’t covered. Larry said we didn’t get the additional money
for phosphorus removal, the interceptor work, those are the 2 biggest missing pieces.
Cathy asked Larry if we are still going to achieve a better phosphorus rate, Larry said, he
can’t tell us on the money side yet, but when we submitted the grant, it was for $6.5 million
for phosphorus removal. That was the total budget including engineering for phosphorus
removal. Roxie goes up twice a week to Onondaga County who is doing a pilot
phosphorus project. The most promising method so far is a lot less expensive than the
filtering method we built the grant proposal around. They use sand to coagulate and the
weight drops it out a lot quicker. Which means we could do everything we need to do in
one phostrip tank. Bill and Larry stopped and saw the project after the Friday meeting.
Bill and Larry believe they can create a revised budget, substantially less.
Cathy asked, with the revised budget, where does that leave us with the partnership deal.
Larry said the rerating gives you the tool to talk about the larger service area driving the
SEQRA process. So we expect within 4-5 months to be rerated, unless we find out
something in the next month with the stress test. Frank asked the 3.1 million increase,
how long would it be before we actually need to use it. Larry said we are not close to
needing it yet. The current plant rating is 10.1 for 30 day maximum average flow, but 25
mgd hydraulic load. Our average flow is 7.5; our highest 30 day max has been 9.2 mgd if
you ignore the runoff event that affected all of Upstate New York in January 1996.
5. Updates on Intermunicipal Agreement Revision
Cathy said they are now meeting every Monday and working through the draft agreement
that Susan Brock put together for us.
6. Staff Reports -
Larry will be meeting with Jerry Hook to work on the belt press specifications.
Larry also mentioned that there was also mix-up during the budget process regarding the
belt press project. The belt press was the 1 thing specified for the total amount of the
capital project, so if you look at Gary’s budget, there is $208,500 of other capital items that
we approved. So we will specify and bid the belt press, establish a firm budget and a
number for that item and then clarify the City budget to include the SJS capital items.
Gary and Larry believe the total dollar amount $630,000 will be the same for the combined
projects.
5
7. Financial Report
Steve handed out a 2000 budget update as of the end of March, shows revenue, budget,
balances, capital reserve balance. Cathy asked that people review at their leisure.
8. Old Business
9. New Business
*Susan Brock Letter
Larry explained that Susan will be the sole proprietor and needs a signature on a letter of
engagement. It is just a change in who the check gets made payable to. Each
municipality should sign it per Dominick Cafferillo. Larry will take and give to Alan to sign
at the DEC meeting Friday, April 28th.
10. Adjournment
All were in favor @ 1:30 pm.
Next regularly scheduled meeting is set for May16th @ 12:30 PM.
1
SPECIAL JOINT SUBCOMMITTEEMAY 16, 2000
A regular meeting of the Special Joint Subcommittee was held on May 16, 2000, at 12:30, at
the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New York
PRESENT: *Frank Liguori, Town of Ithaca
*Mary Gutenberger, City of Ithaca
*Charles Hatfield, Town of Dryden
Don Hartill, Village of Lansing
Mary Russell, Town of Ithaca
Larry Fabbroni, Asst. Super W & S
Dominick Cafferillo, City Controller
Steve Thayer, Deputy City Controller
Gary Gleason, Chief Operator @ IAWWTF
ABSENT: *Joseph Leonardo, City of Ithaca
*Alan Cohen, City of Ithaca
*Ed Hershey, City of Ithaca
*Mark Varvayanis, Town of Dryden
Steve Farkas, Town of Lansing
Ron Anderson, Village of Cayuga Heights
*Cathy Valentino, Town of Ithaca
Dan Walker, Town of Ithaca
Bill Gray, City Superintendent
Brent Cross, Village of Cayuga Heights Engineer
David Herrick, TG Miller PC
Frank opened the meeting and informed who was there, that there was not a quorum.
1. Approval of February & March & April Minutes
2. Updates on SEQR, if any
3. Updates on Regional Planning
4. Updates on DEC Items, if any
5. Updates on Intermunicipal Agreement Revision
2
6. Staff Reports -
7. Financial Report
8. Old Business
9. New Business
10. Adjournment
Next regularly scheduled meeting is set for
1
SPECIAL JOINT SUBCOMMITTEEAUGUST 22, 2000
A regular meeting of the Special Joint Subcommittee was held on August 22, 2000, at 12:30,
at the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New York
PRESENT: *Frank Liguori, Town of Ithaca
*Mary Gutenberger, City of Ithaca
*Mary Russell, Town of Ithaca
Larry Fabbroni, Asst. Super W & S
Dominick Cafferillo, City Controller
Steve Thayer, Deputy City Controller
*Ed Hershey, City of Ithaca
Dave Putnam, Town of Dryden Engineer
*Mark Varvayanis, Town of Dryden
*Cathy Valentino, Town of Ithaca
ABSENT: *Joseph Leonardo, City of Ithaca
*Alan Cohen, City of Ithaca
Dan Walker, Town of Ithaca
Bill Gray, City Super.
Gary Gleason, Chief Operator WWTF
1. Report on May Minutes; Approve Feb, Mar, April
Larry brought up that he would like to prepare summary minutes based on our memory for
the May meeting, because the recorder was not functioning properly. All in all there was
no objection to doing this.
2. Review Budget for Year 2001
Larry reported that Gary and Ron have pretty much prepared the explanations for the
budget in terms of major items. Jose is here to speak about anything to do with the Lab or
Watershed. Cathy asked what created the increases. Larry explained the situation with
the sludge disposal and change in the hauler. The sludge disposal fees are in question
again for the time being. The City of Auburn has built an incinerating facility that can
accommodate 400% of their needs. So they need customers to achieve the scale. They
are currently going through their start-up period and experimenting with different people’s
sludges and what is left after you burn it. Gary has talked in the past that we have well
digested sludge, so when we send it to Auburn there tends to be more ash left as a percent
of what we send in tonage wise, then somebody like Oswego that brings in undigested
sludge.
2
2. Con’t
They are just trying to get a handle of what the true costs are both in the energy it takes to
burn and how much ash is left to dispose of. Because they need to landfill the ash when
done. Auburn has their own landfill for the City of Auburn and they have recently gotten
into a contract to recover gas from that landfill. If they are able to generate gas that is
usable in the incinerator operation, then it could greatly lower the costs for everyone. It is
more of an experimental period right now. We are currently hauling to that facility and
they are charging us $34 per ton. Our carrier who when we don’t haul they do, they are
charging a $2.50 surcharge on what goes to Auburn. It is their way of guaranteeing us
space at the landfill, when we can’t take it to Auburn. As it relates to next years budget,
we still don’t know if we are landfilling or incinerating. $49.50/ton if we landfill (WeCare
hauls), $36.50 up to $40 or so/ton for incineration (IAWWTF hauls).
The letter of intent by We Care (sludge hauler) was handed out.
There were questions about the sludge disposal item. Mary Russell’s concern is the
emissions of incineration in the Auburn area. Larry offered getting more information
about the facility.
We will come back for approval at the October meeting along with the next phase of the
budget. We’ll have the water and sewer consumption and our outside revenue and
outside community figures. Dominick has received the Town of Dryden consumption
figures and is waiting for the Town of Ithaca figures. Dominick will have the debt service
components when we bring the next phase forward.
3. Review of Sludge Disposal System, Short Term, & Long Term RFP
Larry reviewed this item in the budget portion of the agenda. We are kind of in a
predicament with this hauling situation. Larry is recommending that we continue with the
experiment with Auburn and learn more about their “business” and as a result of that we
would write an RFQ for the future hauling contract anticipating that’s probably the start
with 2001. This proposal, in letter form, is the way we would handle sludge disposal for
the interim, $36.50 per ton if we haul it to the City of Auburn or WeCare hauls it to the
Seneca Meadows Landfill for $49/ton.
Larry is hoping for this approval on some way of hauling the balance of the year, knowing
we are going to have a RFQ, for the future. The future does not have to be incineration.
Cathy has no objections to going with this experimental period right now. Neither did
anyone else.
4
4. Review of Watershed Management Efforts
Larry briefly explained that the Town of Ledyard has been heading up all of Cayuga Lakes
Network efforts. There seems to be a little bit going on in the Town of Ledyard that leads
Jose to bring a proposal to this group for an alternative to that.
Jose in brief explained the issue with the Town of Ledyard being such a large project in the
Town scheme of things. Cathy asked why wouldn’t the County be asked to be the lead
agency instead of the City of Ithaca. Larry said it’s more like sponsoring , it seemed more
logical, for the SJS to consider first given the County history on following through on
Watershed improvements.
Ed Hershey mentioned the advantage of being in a position to safeguard our interests at the
south end of the lake.
Frank thought that Tompkins County would be better at being the lead agency, due to the
fact of phosphorus problem being a sticky point for the IAWWTF.
Cathy asked if the SJS approved this, where would it go then. It would go to Common
Council. Cathy agrees with Ed that we have a real vested interest. Cathy is willing to
have this go forward to Common Council. The rest of the voting members were in favor of it
going to Common Council. Ed does feel we need to know what the surrounding areas are
putting into the lake. We know what we are putting into our lake.
5. Status Report on Belt Press Bidding
Larry reported that this is a capital project budgeted item for 2000. We now have almost
the final spec to go out to bid. Once we tie up this item then we can move on to the
balance of the capital project items for 2000. We are working with Stearns & Wheler on
the bid specs. The specs are being prepared more like a contract, with a warrantee,
insurance on transportation etc.
6. Updates on Regional Planning, DEC Items, Intermunicipal Agreements, Short Term
Diversion, etc.
Larry reported that the regional planning group, 6 municipalities, meets roughly once a
month. It is the group that is working through the scope of the EIS that is going to be
prepared for the regional wastewater plan. The makeup of the regional wastewater plan
in some people’s mind is anticipated to be a partnership of 6 municipalities and others think
of 5 municipalities plus Cayuga Heights owning and operating their own plant.
5
6. Con’t
There has been a lot of forward movement in terms of resolutions of the issues that need to
be finalized, perfected, or included in the revised agreement for these 3 parties. So those
discussions about the Intermunicipal agreement follow directly into what we are thinking on
at the regional level. Once this group here perfects a revised Intermunicipal agreement,
then it is anticipated that will provide the frame work for the regional planning group to
expand the contract to 5 or 6 parties. We have been meeting with DEC since the
beginning of the year, to decide on the issues that need to be studied in terms of the
environmental impact for the regional idea of serving the expanded Town of Lansing and a
larger area of the Town of Dryden, all of the Village of Lansing, additional area’s in the Town
of Ithaca beyond what this facility currently is serving, possibly parts of the Village of Cayuga
Heights and naturally the City is fully contained. DEC was initially hammering back at us
about the capacity. We made a lot of positive ground with them to identify the parts of
the programs which are already completed.
We are at the 11th hour of getting the 13.1 mgd of capacity rated for this facility. The
regional people have signed off on it, the Albany people have, in a way, signed off on it.
They need to sit down and write the actual permit. Then there will be a public review
period that is 30-60 days. If that public review period passes without a whole lot of input
or controversy then the permit will go into affect and we will be rated for 13.1 mgd. In
parallel with that, Larry met with DEC and we are making progress on applying for
reimbursement of the funds that already have been granted to interceptor work. We now
have a total of $1.7 million in grants and Larry has been meeting with Tara to work out the
details of the application that would get us that reimbursement. There is the issue of can
we shift some of the money to future work. EFC hasn’t come to any conclusions yet. We
could just get the money and retire the bonds, but we don’t really want to do that at 2.8%.
So there is some discussions that need to go on to convince the financial entity that this is
all a part of the big interceptor program.
Short term diversion was a topic of discussion this morning. There was some attempt to
take the choke hold off the Village of Lansing. Larry’s understanding is, currently the
Village of Lansing has no more sewer permits to give. Cayuga Heights doesn’t feel they are
in a position to give them any more. That gets confused by the fact that Cayuga Heights
figures their reserves based on the zoning of different commercial properties in the Village
of Lansing. Cayuga Heights will rate a property for their need for sewer. For example,
the Pyramid Mall site, Cayuga Heights may say they need to reserve 50 units and Lansing
will only use 26, so though the rest of the units may still be available, Cayuga Heights won’t
let the Village of Lansing use those units elsewhere in the Village. TheVillage of Lansing is
going to go back to the Village of Cayuga Heights and try to convince them one more time.
6
6. Con’t
Those are pretty much the highlights. It is all progress. We have the latest packet from
DEC for the next round of applications. They just came in the mail the other day and are
due back October 31, 2000. The whole basis of the bas plan is solid. Six municipalities
should at least be to the point of agreement and all stand behind the joint application for
additional funds. There is pretty much agreement on a base program in the amount of
$7.4 million of requested additional State Aide. Larry is trying to be optimistic and say that
wherever the negotiations and discussions go, that need for projects and funds is pretty
much common to whatever scenario falls out of it all. If we meet again in September, we
will have a more concrete explanation of what that package would be for your endorsement
and take it back to your respective municipalities for a resolution and support at your
meetings in October.
The guts of what we have asked for, Stearns and Wheler has been helping us through as a
facilitator through all of this and pretty much has outlined. We have $1.4 million for the
phosphorus, we need roughly another $1.3 to fund a total phosphorus removal project at
this facility. So we are saying to the State, if you gives us that additional $1.3, we’ll move
ahead with the total phosphorus job. That is the result of our piloting with Onondaga
County from which we revised the budget and the technology that will treat the total 13.1
mgd as a maximum monthly number, and would treat as much as 30 mgd on a hydraulic
event. That is basically, saying this technology put in one of phosphorus stripping tanks
will treat all of the flows. Cayuga Heights under the same proposal would put in their own
filter for phosphorus if they got funding, we are asking for roughly another million and a half
dollars for interceptor work for interceptor work if we make that application and the
Lansings would ask for another million and a half dollars for their sewers. It is a pretty
balanced package of requests that we are going after for an additional $7.4 million in Bond
Acts Funds, if we can reach an agreement to make that application by October 31st. Larry
has tried to dwell on things you have heard already either once today or recently.
7. Staff Reports
Larry reported on Gary’s health condition. Ron, Jose and Jeff are proceeding with keeping
things in line at the facility.
8. Financial Report
Dominick handed out the status report of the plant rerating project that Cathy requested
from Dominick.
9. Old Business
7
Nothing to report.
10. New Business
Nothing to report.
11. Adjournment
Meeting adjourned 2:05 pm.
Next regularly scheduled meeting will be September 26, 2000.
1
SPECIAL JOINT SUBCOMMITTEESEPTEMBER 26, 2000
A regular meeting of the Special Joint Subcommittee was held on September 26, 2000, at
12:30, at the Ithaca Area Wastewater Treatment Facility, 525 Third Street; Ithaca, New
York
PRESENT: *Frank Liguori, Town of Ithaca
*Mary Gutenberger, City of Ithaca
Larry Fabbroni, Asst. Super W & S
Dominick Cafferillo, City Controller
Steve Thayer, Deputy City Controller
*Mark Varvayanis, Town of Dryden
Charlie Hatfield, Town of Dryden
*Cathy Valentino, Town of Ithaca
Bill Gray, City Superintendent
Gary Gleason, IAWWTF Chief Operator
ABSENT: *Joseph Leonardo, City of Ithaca
*Mary Russell, Town of Ithaca
*Alan Cohen, City of Ithaca
*Ed Hershey, City of Ithaca
Dan Walker, Town of Ithaca Engineer
There is not a quorum to make a motion of approval.
1. Cathy started the meeting off regarding her conversation with Sylvia and the City taking
the lead for the Cayuga Lake I/O. She is very eager for the City of Ithaca to become the
lead agency and it would really move the project forward. Cathy said she felt very
comfortable with the situation after speaking with Sylvia.
2. Budget 2000 Review
Dominick handed out the 2 options available for approval.
2
Dominick said we didn’t adjust the operating budget substantially. The two line items in
the operating budget that have been changed thus far is line #435-Contractual Services
increased to $313,769-due to the labor wages increasing and #499-sludge disposal
decreased to $231,000. If we do run into trouble with our sludge disposal, we’ll have to
use a portion of the contingency, which is on page 2, which is $50,000. This is similar to
what we did last year. We do not know exactly what that cost per ton is going to be, but
rather than increase the budget, we will cover it with contingency. We haven’t used the
contingency in recent memory. Other than that, we did not change the treatment plant
expenditure portion of the budget.
On page 1 of the revenues, option #1-the septage hauling outside revenue was left at
$200,000. In looking at the year-to-date figure we seem to be running slightly behind.
However, investment interest rates are higher. The shared payments from the City and
the Towns which are based on usage, are another component of income that is holding
steady.
Cathy asked Dominick how he figures the interest payment, debt service. Dominick said
we pay it out of the City’s part and charge back.
Bill had a few questions about the #225 account, Other Equipment. He was inquiring
about the $34,000 increase. Gary explained the 4 wheel drive truck with plow and hazard
materials transportation. Bill asked if $10,000 would be enough of an increase for utilities.
Gary thought so.
Dominick mentioned that this will be a recommendation to the BPW.
Cathy posed the question to the partners - the possibility of allocating a fairly substantial
amount of fund balance next year or would we rather allocate a lesser amount of fund
balance next year and have the extra be in the rate differential. The other question being,
should we pass the rate increase onto our customers.
Cathy said she needs to go back and look at her budget figures. Dominick said the actual
rate gets set the first of November. Cathy will have hers done by the 15th. Dominick said
this budget will go to Council in October.
Cathy asked why we didn’t have any capital projects this year. It was pointed out that we
do have a list of projects, attached to the original submitted budget.
The meeting was adjourned.
1
SPECIAL JOINT SUBCOMMITTEEOCTOBER 31, 2000
A regular meeting of the Special Joint Subcommittee was held on October 31, 2000, at
12:30, at the Town of Ithaca; Town Hall; Ithaca, New York
PRESENT: *Mary Russell, Town of Ithaca
*Cathy Valentine, Town of Ithaca
Dominick Cafferillo, City Controller
Larry Fabbroni, Asst. Super W & S
Steve Thayer, Deputy City Controller
Dan Walker, Town of Ithaca
Ed Hershey, City of Ithaca
ABSENT: *Joseph Leonardo, City of Ithaca
*Frank Liguori, Town of Ithaca
*Alan Cohen, City of Ithaca
*Mary Gutenberger, City of Ithaca
*Mark Varvayanis, Town of Dryden
Bill Gray, City Superintendent
Gary Gleason, C.O. IAWWTF
There is not a quorum to make a motion of approval.
There was no agenda so the following is a recap of the minutes per the tape.
Cathy said that she asked Dominick which option 1 or 2 was in the City Budget. Dominick
replied with Option #2, which leaves the rate the same as the previous year, which uses
more fund balance. Dominick added that it gives the other municipalities the option of
handling their overall rate as they chose. We chose to increase our rate, which will
contribute more to the collection system capital reserve and pay less to the joint activity
and will in turn use more fund balance to balance the wastewater treatment plant budget.
2
Mary asked about the Return To General Fund line, what is that for exactly. Dominick said
a percentage of allocation for various services; Payroll, Human Resources, legal services, etc,
distribution of various overhead costs at a percentage. This all includes a fair percentage
of the cost of operating and maintaining our computer system and network. The prime
reason for the percentage increase, was an expansion of the Human Resource Department
of 3 positions and the Information Technology Department of 2 positions. Dominick will
furnish a printout. The overhead costs are shared by the Fire Department, Youth Bureau,
Water & Sewer, Joint Activity etc. All of the non-general fund activities or the activities
that are shared beyond the City. Mary also questioned the salary for the Landscape
Planner and how it benefits the Town. Larry replied that the position was revised to an
Environmental Analyst and is in final Civil Service evaluations & involved with both critical
science watershed activities and Lab support. Presently roughly 40% of the salary is being
charged to the Water Treatment Plant Payroll.
Cathy thought there should be some kind of agreement for the percentage of the positions
that the work in the different facilities. Cathy also thought for any employee who has their
salary broke out with different departments, be shown.
Cathy asked where she would find the revenue on the charge out of the Landscape Planners
time. Larry and Dominick explained that the weekly payroll charges the appropriate water
or sewer account. Larry noted that this position is fully funded in the Joint Activity Budget;
however; the deliberate process of water merger has left daily lab work to cover at the
Water Plant. For 2000 and 2001, the effects of the Joint Activity Budget carrying part of a
full time professional and seasonal lab help is a net earnings. Dominick said we are going
to spend less of the appropriations. At the actual time it is charged out 50% here and 50%
somewhere, then the actual expense is going to be less. It will not be seen on the revenue
sheets.
Cathy said that when she looked through the annual report, she noticed that there were
bonds expiring May 15, 2006 and interceptor bonds that are expiring 2017, is that right.
Larry said, some of that is the original debt to the plant, Dominick spoke up and said Cathy
might be looking at the retirement debt service beginning 1992, which is 15 years. Again,
Cathy would like a break down of what debts are outstanding and the payment schedules.
Dominick indicated this is always available and has been provided from time to time.
Mary had a question on the capital projects items - driveway blacktop sealing. Larry said
that was for the overall oil and stone treatment, a 10 year improvement, to seal the asphalt
which has aged since 1987.
Cathy would like breakouts for the Return to General Fund, percentages of people’s salaries
as close as you can estimate it and the bonds and a repayment schedule. Dominick
3
mentioned that the Return to General Fund is a once a year charge, whereas the salaries for
direct work of operation are allocated on a weekly basis.
Cathy mentioned that she was pleased to go with Option #2.
The meeting was adjourned @ 12:37 p.m.