TB Resolution 2022 - 084: Authorization to Award Contract for the Public Works Facility Fueling Station Design Project
Whereas on April 20th, 2022, the Director of Engineering (Director) received proposals for the Town of Ithaca Public Works Facility Fueling Station Design Project (Project), and
Whereas Barton and Loguidice, D.P.C (B&L) was the only firm to submit a proposal, and
Whereas B&L has adequality outlined related work experience, project objectives, timelines, and knowledge of fuel station design that meet and/or exceed our expectations, and
Whereas B&L has successfully analyzed and designed numerous fueling stations for surrounding municipal operations, and
Whereas Staff have reviewed the proposal and qualification of the B&L and recommends award of Part A, fixed fee: $14,992.60 (for the review and analysis of the fuel station storage requirements,
site location, associated impacts, and permit requirements) to B&L, and
Whereas Part B of the proposal may be considered for award at a later date based on the findings of Part A, now, therefore, be it
Resolved that the Town Board authorizes the award and execution by the Supervisor of a contract for Part A of the Project to Barton and Loguidice, D.P.C, 443 Electronics Parkway, Liverpool,
NY 13088, subject to approval of the contract documents by the Director and Attorney for the Town, and be it further
Resolved that the Director is authorized to increase the fixed fee by a lump sum value of $500.00 for an additional meeting with the consultant if deemed necessary.
Moved: Bill Goodman Seconded: Eric Levine
Vote: ayes – Goodman, Levine, Johnson, Howe, DePaolo, Bleiwas and Rosen